PLTS SIMULATION HYBRID USE SYSTEM ADVISOR MODEL (SAM) AT THE BOBA STORE IN WEST SUMBAWA

Authors

  • Rifki wikra wardana Universitas Teknologi Sumbawa
  • Muhammad Hidayatullah Universitas Teknologi Sumbawa
  • Paris Ali Topan Universitas Teknologi Sumbawa
  • Titi Andriani Universitas Teknologi Sumbawa

DOI:

https://doi.org/10.51401/altron.v2i02.3208

Keywords:

Biaya Kelistrikan Kedai Boba, PLTS hybrid dan Simulasi software SAM

Abstract

Boba's shop is a business that requires a large amount of electrical energy, such as room lights,
street lamps, decorative lights, presses and refrigerators, resulting in large electricity bills. To
analyze electricity costs, research was carried out at a boba shop by simulating a hybrid PLTS using
SAM Software. The simulation results show that the weather is favorable or solar radiation at that
location is quite high. In September the solar radiation is very high to generate power of 190kWh
and the lowest is in December of 132kWh. The power requirement at the boba shop is around
2.38kWh/day based on calculations on the monthly load at the boba shop according to data from
PT. PLN (Persero) ULP Taliwang. If the PLTS with solar panels with a capacity of 300Wp totals 4
units, the VRLA Gel 12V x 100AH batteries total 4 and are simulated according to weather data at
the boba shop location to produce around 1,933kWh per day in one year and the PLTS construction
costs $ 4,592. The application of hybrid PLTS to boba shops will be very good, because most of
them can be backed up by PLTS and only a small portion requires energy from PLN so that the
electricity costs that must be incurred are only IDR 76,569.1 in 1 year

References

Radwitya Erick.(2020). Perancangan PLTS On Grid Dilengkapi Panel ATS di Laboratorium Teknik Elektro Politeknik Negeri Ketapang. Journal of Electrical Power, instrumentation and Control. Ketapang.

Pramudita Aji Brahmantya dkk,.(2020). Analisis Ekonomi On Grid Plts Untuk Rumah 2200 Va.Listrik. Instrumentasi Dan Elektronika Terapan. Vol. 1, No. 2, Desember 2020

System Advisor Model, (2020).batteries in SAM 2020.2.29: Behind-the-Meter System. http//youtu.be/eURDJucc-jg.

Umair Shahzad, (2022), Analysis of Solar System Models Using System Advisor Model Simulations. Volume 9, Issue 31, pages 23-32.

Firmani Muhammad Dan Irfansyah Muhammad. ( 2021). Perancangan Sistem Hybrid Pembangkit Listrik Tenaga Surya Dengan Turbin Angin Terapung. Jurnal Teknik Mesin UNISKA. Vol 6 No 2. Kota: Banjarmasin.

Duka Abit Timotius Erik., Dkk. ( 2018) . Perancangan Pembangkit Listrik Tenaga Surya Hybrid Pada Area Parkir Gedung Dina's Cipta Karya. E-Jurnal Spectrum. Dina's Bina Marga Dan Pengairan Kabupaten Bandung. Vol 5 No 2. Universitas Udayana.

Naim Muhammad. (2020). Rancangan Sistem Kelistrikan PLTS Off Grid 1000 Watt Di Desa Loeha Kecamatan Towuti. Vertex Elektro. Vol 12 No 01. Akademik Teknik Sorowako.

Santosa Tri Nugroho Andry., Dkk.( 2022). Perencangan Sistem PLTS Off Grid Kapasitas 100 wP Sebagai Sumber Energi Alternatif Charging 220 V Di Daerah Terdampak Bencana Semeru. Prosiding Seminar Nasional Aplikasi Sains & Teknologi. Kota : Yogyakarta.

Rizky Ryan., Dkk. (2022). Analisis PLTS ON GRID. Volume 14 Nomor 1. Muhammadyah Makasar.

Chamdareno Gagani Prianh Dan Hilal Hamza. (2018) . Analisis Pembangkit Listrik Tenaga Hybrid PLTD -PLTS di Pulau Tunda Serang Banten. Resistor (Elektronika Kendali Telekomunikasi Tenaga Listrik Komputer). Vol. 1 No 1. Universitas Muhammadyah Jakarta.

Andre Setiawan Dan Agus Alinuha. ( 2022). Jurnal Ilmiah Teknik Elektro. Pembangkit Listrik Tenaga Surya Off Grid Untuk Supply Charge Station. Vol 1. Universitas Muhammadyah Surakarta.

Fuaddin Daryal dan Daud Aceng.(2020). Rancangan Sistem Pembangkit Listrik Tenaga Surya On Grid Kapasitas 20 kWp Untuk Residensial. Jurnal Energi. Volume 10, No 1. Bandung.

Celebrities.(2022).Rumus Cara Menghitung Nilai Rata-rata Dengan Benar.https://www.celebrities.id.

Instalisasi listrik TV,( 2021), Cara menghitung Jumlah Baterai PLTS. http://youtu.be/nwcHMV6WA5c.

Halim Levin dan Oetomo. (2020). Perancangan Dan Implementasi Awal Solar Inverter Untuk Pembangkit Listrik Tenaga Surya Off Grid. Jurnal Teknologi. Vol 12 no 1. Universitas Muhammadyah Jakarta.

Published

2023-08-09

How to Cite

Rifki wikra wardana, Hidayatullah, M., t, P. A., & Andriani, T. (2023). PLTS SIMULATION HYBRID USE SYSTEM ADVISOR MODEL (SAM) AT THE BOBA STORE IN WEST SUMBAWA. Journal Altron; Journal of Electronics, Science & Energy Systems, 2(02), 137-144. https://doi.org/10.51401/altron.v2i02.3208