COST AND TIME ANALYSIS OF ROAD IMPROVEMENT PROJECTS USING THE EARNED VALUE METHOD

Authors

  • Dinda Fardila Universitas teknologi sumbawa
  • Siti Nurholisa R Kamagi Universitas Teknologi Sumbawa
  • Paris Ali Topan Universitas Teknologi Sumbawa
  • Zainuddin Husainy Universitas Teknologi Sumbawa

DOI:

https://doi.org/10.36761/hexagon.v5i2.4044

Keywords:

Cost Time Performance, Earned Value Method, Microsoft Project.

Abstract

Cost and time are important variables in a construction project. Significant cost and time deviations can indicate poor project management, so there is a need for evaluation and control regarding this matter. In this research, researchers evaluated costs and time using the Earned Value Concept method. Performance evaluation of time and cost was carried out using Microsoft Project. Cost performance using the Earned Value Method means that there is a cost overrun of IDR 1,206,432.85 from the total construction budget plan (overbudget). This is shown by the EAC (Estimate to Complete) value of IDR 11,536,477,946.05 which is greater than the BAC (Budgeted All Construction) value of IDR 11,535,271,513. Performance when using the Earned Value Method has SV values ??in the July-October period showing positive values, namely IDR 175,140,527.07, IDR 175,138,345.20, IDR 175,140,527.07, IDR 32,838,848.83, this value shows that the project was realized faster than planned. Performance based on the schedule productivity index (SPI) in the July period has a value of 1.037894631, August has a value of 1.02648206, September has a value of 1.019104588, and October has a value of 1.002926831. This SPI value shows >1, meaning that the realized work productivity is carried out faster than the planned schedule.

References

Arsjad, T. T., & Malingkas, Y. G. (2020). Pengendalian Biaya Dan Waktu Pada Proyek Pembangunan Ruko Di Area Perumahan Kharisma Koka Minahasa Menggunakan Metode Konsep Nilai Hasil. Jurnal Sipil Statik, 8(1), 53–64.

Arthono, A., & Saputra, B. P. A. (2023). Analisis Kinerja Proyek dengan Metode Earned Value: Studi Kasus Proyek Pembangunan Unit Sekolah Baru SMKN Kec. Serpong Kota Tangerang Selatan. Jurnal Teknik Sipil Terapan, 5(2), 68. https://doi.org/10.47600/jtst.v5i2.608

Atmaja, J., Suhelmidawati, E., Alexander, H., Natalia, M., Misriani, M., & Hanika, R. N. (2020). Analisa Kinerja Proyek Menggunakan Metoda Earned Value Management dan Pengendalian dengan Metoda Time Cost Trade Off (Studi Kasus Proyek Pembangunan Jembatan Silaosinan Kabupaten Mentawai). Jurnal Teknik Sipil ITP, 7(2), 85–95. https://doi.org/10.21063/jts.2020.v702.06

Durdyev, S. (2020). Review of construction journals on causes of project cost overruns. Engineering, Construction and Architectural Management, 28(4), 1241–1260. https://doi.org/10.1108/ECAM-02-2020-0137

Hamrozi, M. N., & Adistana, G. A. Y. P. (2022). Pengendalian Biaya dan Waktu Proyek dengan Metode Earned Value (Studi Kasus: Pekerjaan Design and Build Interior Kantor Pusat PT Pelabuhan Indonesia III (Persero) di Gedung Perkantoran Pelindo Place). Rekayasa Teknik Sipil, 4(2), 1–11.

Maromi, I. M. I. R. (2015). Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya. Jurnal Teknik ITS , 4(1), 2337–3539. https://media.neliti.com/media/publications/213460-metode-earned-value-untuk-analisa-kinerj.pdf

Massie, M., Manoppo, F. J., & Dundu, A. K. T. (2022). Studi Penerapan Pengendalian Waktu, Biaya, Dan Mutu Pelaksanaan Proyek Boulevard Pantai Amurang Kabupaten Minahasa Selatan. Jurnal Ilmiah Media Engineering, 12(1), 2087–9334.

Priyo, M., & Indraga, K. F. (2015). Analisis Kinerja Biaya dan Jadwal Terpadu dengan Konsep Earned Value Method (Studi Kasus: Proyek Pembangunan Gedung). Jurnal Ilmiah Semesta Teknika, 18(2), 106–121.

Proaño-Narváez, M., Flores-Vázquez, C., Vásquez Quiroz, P., & Avila-Calle, M. (2022). Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings, 12(3). https://doi.org/10.3390/buildings12030301

Syaiful, A. (2018). Analisis Penjadwalan Ulang Dengan Menggunakan Metode PERT (Program Evaluation And Review Technique) (Rescheduling Analysis With PERT Method). In Universitas Islam Indonesia.

Wowor, F. N., Sompie, B. F., Walangitan, D. R. O., & Malingkas, G. Y. (2013). Aplikasi Microsoft Project Dalam Pengendalian Waktu Pelaksanaan Pekerjaan Proyek. Jurnal Teknik Sipil, 1(8), 543–548.